CERN Accelerating science

This website is no longer maintained. Its content may be obsolete. Please visit http://home.cern/ for current CERN information.

CERN Accelerating science

World’s first crabbing of a proton beam

The first test of superconducting crab cavities to rotate a beam of protons was performed on 23 May using a beam from CERN’s Super Proton Synchrotron (SPS) accelerator. These cavities are a key component of the High-Luminosity Large Hadron Collider (HL-LHC). A total of 16 such cavities will be installed in the HL-LHC – eight near ATLAS and eight near CMS.

Figure 1: DQW Crab Cavity Prototype being assembled at CERN.

In the LHC and HL-LHC, the two counter-rotating bunches collide at an angle at each collision point of the experiments. When installed at each side of the ATLAS and CMS experiments, the crab cavities will “tilt” bunches of protons in each beam to maximise their overlap at the collision point thus increasing the luminosity. The crab cavities are expected to increase the overall luminosity by 15 to 20% and improve the quality of data collected by the experiments. Crab cavities were already used in the KEKB collider in Japan for electrons and positrons, but never with protons, which are more massive and at significantly higher energies.

Figure 2: The Crab Cavity Cryostat installed on a movable table in the CERN SPS.

The first crab cavity prototypes were manufactured at CERN in 2017 in collaboration with STFC and USLARP. The cavities were assembled in a cryostat and tested at CERN-SM18 facility prior to its installation into the SPS. The cavities were installed in the SPS accelerator during the last winter technical stop for machine development studies in the SPS.

Figure 3: Images a bunch in the CERN SPS for 2 different voltage settings in the Crab Cavities. Left without voltage and deflection. Right with 1MV voltage and deflection.

 

The first beam tests were performed on 23 May at 4.5 K with a single proton bunch accelerated to 26 GeV and with a bunch intensity of 0.2-1×1011 p/b. The crab cavities were powered to about 10% of their nominal voltage in the first tests and later increased to up to 50% limited mainly due to vacuum rise. The “crabbing” was observed using head-tail monitor with large enough bandwidth and resolution to observe the intra-bunch orbit induced by the crab cavities. These tests mark the start-up of a unique facility for testing superconducting cavities on a high-current, high-energy proton beam. The results mark an important milestone to prove the feasibility of using such cavities with long proton bunches for increasing the luminosity in the HL-LHC.

In the coming months, the cavities will be commissioned to their nominal temperature of 2K and slowly ramp the kick voltage to their nominal voltage of 3.4 MV. During the rest of the year, the cavities will undergo a series of tests to fully validate their operation for a robust operation in the HL-LHC era.  

Martin Bellwood (University of Liverpool)
AVA – Training (anti)matters
6 Mar 2018

AVA – Training (anti)matters

Early stage AVA researchers benefit from established and bespoke training events

Panagiotis Charitos
FCC Week 2019 accelerates progress towards post-LHC colliders
12 Jul 2019

FCC Week 2019 accelerates progress towards post-LHC colliders

Academic and research institutes, industrial partners and funding agencies met in Brussels for the Future Circular Collider (FCC) study annual meeting.

Panagiotis Charitos (CERN)
Advancing superconductivity for future magnets
8 Oct 2018

Advancing superconductivity for future magnets

Collaboration between researchers and industry is key for unlocking the potential of this technology.

From first concept to the SPS: the challenge of the HL-LHC crab cavities cryomodules

The first concepts of the HL-LHC crab cavities started more than 10 years ago. They were the fruit of the discussions of a young physicist at BNL and a beam dynamics expert at CERN. The concept was not new but using it for the LHC implied a long journey of technological challenges.

The distance between the LHC beams required a new RF concept for particle deflection with a novel shapes and significantly smaller in size than conventional RF cavities. The challenge was taken with enthusiasm by the RF community resulting no less than 10 concurrent designs from RF experts across three continents. In 2013, three designs were considered to be the most adapted to the LHC and became ready for the development of a proof of principle. While this may sounds like a moment of fierce competition, in reality it showed the spirit of cooperation towards a common goal among the members of our community. The results of the RF tests of the Double Quarter Wave (DQW), the RF Dipole (RFD), and the four Rod (4R) were highly promising and analysed by an international panel in 2014 that recommended to focus the efforts on the first two designs to make a full validation of the cryomodule in the CERN’s SPS.

One of the crab cavities that will be used in the HL-LHC (Image Credit: CERN)

The entire community concentrated on the two designs and on the development of the concept of all the other required components of the cryomodule that should host the cavities. The effort that had already started in 2013 by CERN required the knowledge, experience and imagination of the collaboration.

In fact, 2015 became a decisive year that started with a collaborative design thinking of the most innovative components. Among them we can highlight the frequency tuning system, the helium tank and the RF lines, all of which required inspiration beyond the conventional wisdom to adhere to the strict needs of HL-LHC. There is a global consensus on the fond memories of the design phase in 2015, wild enthusiasm and collaboration. Effectively, during this extremely critical period every team contributed to the design before concentrating on the detail development of the different components. The result was as harmonic as the sound of a good symphonic orchestra. A robust design that was flexible to be used for the test of the cryomodule at the SPS, easily adaptable for the LHC and that could be transferred to the industry for the series production.

Today the first cryomodule is finished and under cold test without any delay on the manufacturing plan that was prepared more than two years ago. A plan that at that moment was considered almost impossible. Today, the infrastructure in the SPS is ready and just waiting for the cryomodule installation. The hard work of these last 5 years of engineers and physicists from US, UK and CERN will reap the benefits of their hard efforts.

In the meantime, the team is thinking about the future. In December the industrial contract for the series production of the cavities under CERN’s responsibility will be adjudicated. The global collaboration will be further enlarged with discussions with laboratories in Canada and in Japan willing to contribute to the construction of the cryomodule.

A global effort and we hope a global success!

Isabel Bejar Alonso (CERN)
A new step for High-Luminosity LHC
10 Dec 2018

A new step for High-Luminosity LHC

...a worldwide project to enhance LHC potential to discover. The 8th HL-LHC Collaboration Meeting took place last October, in Geneva.

Panos Charitos (CERN)
EASITrain gears up following mid-term review
12 Dec 2018

EASITrain gears up following mid-term review

The meeting offered the opportunity to young researchers to present their latest work.

Massimo Sorbi (CERN, INFN), Marco Statera (INFN) and Ezio Todesco (CERN)
A new step towards successful MgB2 superconducting coils
12 Mar 2018

A new step towards successful MgB2 superconducting coils

MgB2 coil successfully tested at LASA for the round coil superferric magnet correctors